Next Project

Rostov-on-Don
Airport Complex Yuzhny

Project map - Airport Complex Yuzhny
General Contractor:
LLC «MARASHCHSTROY»
Client:
MC Airports of Regions JSC
Project Implementation Timeline:
July 2015 – October 2017

Project Characteristics

87 000 м2
Area of completed works
850
Number of Parking Spaces
68 000 м2
Volume of Monolithic Works

Project Description

Execution of turnkey design and construction works with premises prepared for finishing, including the full scope of electromechanical works, under a general contract agreement.