Next Project

Nizhny Novgorod Region, Kstovo
New Production and Technological Complex, part of Novogorkovskaya CHPP

Project map - New Production and Technological Complex, part of Novogorkovskaya CHPP
General Contractor:
LLC «MARASHCHSTROY»
Client:
EKS SOYUZ JSC
Project Implementation Timeline:
February 2013 – May 2014

Project Characteristics

10 000 м2
Area of completed works

Project Description

Installation of foundations for heat recovery steam generators, foundations for flue gas ducts, anchor for static testing of an overhead crane, foundations for gas turbine units.