40 000
Area of completed works
630
Number of Parking Spaces
Project Description
- Demolition works, laying of power supply cables and low-current networks - 58,000 m (Phase I)/4,000 m (Phase II).
- Installation of lighting poles - 118 pcs. (Phase I)/ 32 pcs. (Phase II).
- Laying of heating network utilities - more than 4000 m (Phase I)/950 m (Phase II).
- Laying of domestic and storm sewer lines - 6000 m (Phase I)/719 m (Phase II) area of improvement.