Next Project

Novy Urengoy
Construction of Facilities of the Novy Urengoy Airport Complex

Project map - Construction of Facilities of the Novy Urengoy Airport Complex
General Contractor:
LLC «MARASHCHSTROY»
Client:
MC Airports of Regions JSC, Urengoyaeroinvest LLC
Project Implementation Timeline:
November 2020 – December 2022

Project Characteristics

19 583 м2
Area of completed works
300
Number of Parking Spaces
12 000 м2
Volume of Monolithic Works

Project Description

Adjustment of design documentation with passing the State Expert Review, development of working documentation in BIM, execution of turnkey construction works, including the full scope of electromechanical works, under a general contract agreement.